HWY 182 BRIDGE UPDATE

5/14/2018

WIS 182, Park Falls (*updated*)

WIS 13 to Saunders Avenue

North Fork Flambeau River Bridge

 

Scheduled ahead

  • Bridge staining is currently scheduled to begin on Monday, May 14.
  • Remaining roadwork is currently scheduled to begin on Monday, May 21. The contractor will be removing pavement and placing concrete approach slabs.
  • Crews will also be constructing the remaining curb and gutter and sidewalk.

Traffic impacts

  • During the week of May 21 and May 28, motorists on WIS 182 can expect to encounter single lane closures controlled by temporary stop lights between 2nd Avenue and Case Avenue.
  • During the week of June 4, crews will complete milling and paving operations on WIS 182 from WIS 13 to Saunders Avenue under flagging operations.
  • Construction is currently scheduled for completion on June 8, 2018.
  • This schedule is based on favorable weather conditions and construction progress.

 

Information and resources


Business and property owners can contact:
• WisDOT Project Manager Dan Erva at 715.365.5776

  • Project Leader (in the field) Erik Lundwall at 715.299.3444